After the wind tunnels in the SIM building and Innovation Hub were donated or lost, Dr. Rajadas requested a new wind tunnel be designed, developed, and fabricated using facilities and resources available on ASU Polytech. Over 6 months, a single

After the wind tunnels in the SIM building and Innovation Hub were donated or lost, Dr. Rajadas requested a new wind tunnel be designed, developed, and fabricated using facilities and resources available on ASU Polytech. Over 6 months, a single student was tasked with running the CAD modeling process, undergoing the revision stages, and welding/fabricating the tunnel by the end of Fall 2021.

Reuse Permissions
  • Included in this item (2)


    Details

    Title
    • The Fabrication and Delivery of a Wind Tunnel for ASU Polytechnic Engineering Curriculum Purposes
    Contributors